From: Dave Gill <drgill@triumf.ca>
Date: Fri, 17 Apr 1998 13:50:58 -0700
To: e614meetings@phys.ualberta.ca
Subject: AGENDA

E614 Collaboration Meeting
                     April 24-25, 1998
                     TRIUMF Auditorium.

[] - session coordinator
() - presenter

Friday April 24, 1998
 9:00   Welcome                                          (Dave G.)

 CHAMBERS.                                     [Vladimir S./Pierre A.]
    Meeting Prime GOAL: Finalize design and schedule.
_______________________________________________________________________
-----------------------------------------------------------------------
A. Results of Monte Carlo analysis                       [Dennis W.]
 9:20 DME buffer zones - impacts chamber design          (Dennis W.)

 9:40 Field wires/no field wires - impacts chamber design
       1. Monte carlo results                            (Dennis W.)
       2. Comments                                       (Vladimir S.)
       3. Discussion *(decision after test results presented)

10:00 He gap sizes - impacts assembly design & total wire count.
       1. The 464 proposal                               (Dennis W.)
                   Impact on number of chambers required.
       2. Resolution in non-uniform B field.             (Dennis W.)
       3. Mechanical constraints.                        (Jan S.)
       4. Discussion

10:25 COFFEE Break

10:40 Muon tracking - impacts assembly design
       1. Summary of past results                        (Dennis W.)
       2. Muon ID (SiLi or not)                          (Anuj P.)
       3. Muon spin optimization                         (Anuj P.)
       4. Mechanical constraints                         (Jan S.)
       5. Discussion
_______________________________________________________________________
-----------------------------------------------------------------------
B. Results from chamber test                             [Maher Q.]

11:10 Data Analysis                                      (Maher Q.)
         Calibrations - Garfield vs data
         Tracking - Wire mapping (plane 4 misalignment?)
         Efficiencies - Impact on number of chambers required.
        *Field wires/no field wires.
         Discussion - decision REQUIRED

12:00 LUNCH Break

13:00 Comments on test stack noise problems.             (Grant S.)

13:10 Comments on cross talk.                            (Vladimir S.)

13:20 Discussion
_______________________________________________________________________
-----------------------------------------------------------------------
C. Design considerations                                 [Pierre A.]

13:30 Mechanical; - impacts chamber design                
       1. New G10 pieces                                 (Pierre A.)
                 - Motherboard support (preamps),
                   DME containment, 
                   He gas containment and
                   HV foil support.
                 - Impact on assembly procedure          (Vladimir S.)
       2. Lamel manufacture - multiple pieces.           (Pierre A.)
       3. Signal extraction                              (Pierre A.)
                    - to preamps and
                    - to TDC/ADC's
       4. Discussion - decision(s) REQUIRED

15:00 COFFEE Break

16:00 Gas System; - impacts chamber design               (Robert O.)
       1. Required flow rates for DME and He.
       2. Monitoring of Temperature and Pressure.
       3. Recycling possibilities. 
       4. Discussion

16:40 Electronics; - impacts chamber design
       1. VTX & KIAE = 1st choice.                       (John S.)
       2. HV distribution and test pulse schemes         (Pierre A.)
       3. Wire count & multiplexing (VTX availability).  (Vladimir S.)
       4. Discussion - decision(s) REQUIRED

17:45 Review of the days decisions                       (Dave G.)

19:00 Dinner at Poutissou's

Saturday April 25, 1998
 9:00 Review of yesterdays decisions                     (Dave G.)
            ***Anyone have second thoughts?***
_______________________________________________________________________
-----------------------------------------------------------------------
D. Schedules, milestones and future plans
 9:30 Chambers.                                          [Vladimir S.]
       1. Construction program.                          (Vladimir S.)
       2. Testing schedule                               (Pierre A.)
             Foil tension, gas diffusion, gas separation,
             Sources, cosmics and beam exposure.
       3. Discussion

10:00  PC's   - impacts assembly design
       1.  Central PCs                                   (Vladimir S.)
             Needed or not? Impact on target changing.
       2. Outer PC's                                     (Vladimir S.)
             Number of wires/plane & multiplexing.
             Time zero for muons & positrons? 
       3. Discussion


10:30 COFFEE Break

10:45 Spectrometer.                                      [John M.]
       1. Magnet shield;                                 (John M.)
             Cylinder vs box - advantages/disadvantages.
             Chamber access - cantilevered vs tracks     (Jan S.)
       2. Magnet purchase status.
       3. Alignment/Mounts                               (Peter K.)
             Magnet in Shield
             Spectrometer to beam.
             Chambers in magnet
       4. Discussion - team building.

11:15 Software management.                               [Renee P.]
       1. Data Acq. & Slow Controls                      (Renee P.)
       2. Circuit/Trigger                              (Jean-Michel P.)
       3. Future plans for Analysis Software             (Maher Q.)

12:00 LUNCH Break

13:00   Software management. (continued)                 [Renee P.]
       4. Software management                            (Renee P.)
       5. Discussion - team building.

13:30 Status of Monte Carlo Code                         [Dennis W.]
       1. Setup on LIN01/plans for future machines       (Renee P.)
       2. Digitization                                   (Dennis W.)
       3. Discussion - team building.

14:00 The muon beam.                                     [Nate R.]
       1. Mu beam Monte Carlo status (Tune/Rate/Purity). (Nate R.)
                  pion(muon) production                  (Dennis W.)
       2. Plan for beam tests                            (Dave G.)
            May - M11 surface muons (Rate/Purity).
            July - M11 surface muons & their polarization.
       3. Discussion - team building.

14:45 Physics.                                           [Dave G.]
       1. First experiment?
              Depolarization in helium - an experiment   (Dennis W.)
       2. Systematic studies required                    (Dave G.)
       3. Discussion - team building.

15:30 COFFEE Break

15:45  Collaboration Business.                           (Dave G.)
         Making decisions between collaboration meetings.
       1. Hardware - (coordinator's responsibility)
       2. New collaborators & students
                 (Spokesmen/Institutional coordinators.)
                     Commitments (Acceptable %'s)
       3. Publications - conference papers.
       4. Budgets.
       5. Discussion - team building.

   Date of next collaboration meeting.


AGENDA / Dave Gill