Run Plan for December 2002: (last updated 2 Dec) - Change field to 1.96 T. (couple hours) (finish midday, Mon 2 Dec) [Magnet people] - (Almost) full data set with B=1.96T (for energy calibration etc.). (2 days) (finish morning, Wed 4 Dec) - Change field to 2.04 T during 4 Dec MAINTENANCE DAY. (few hours?) [magnet people] (finish afternoon (evening?), Wed 4 Dec) - In parallel with the field change, switch the PC gas to Ar/ISO. No shifts during this period. (18 hours) [RO] (finish midday, Thu 5 Dec) - Take some data at various high voltages with the new PC gas. [Dave Gill] (finish evening, Thu 5 Dec) - Change PC gas back to CF4/ISO. No shifts during this period. (18 hours) [RO] (finish midday, Fri 6 Dec) - Full data set with B=2.04T surface muons (for energy calibration, acceptance studies, etc). (2 days) (finish morning, Mon 9 Dec) - Ramp field down to zero. (All day.) (Finish afternoon, Mon 9 Dec) - Pion, positron, and surface muon data, for alignment, efficiencies, and other comparisons. (Note that this will be with Ar/ISO in the PC's!) (1 day) (finish morning, Tue 10 Dec) BEAM OFF 10 December, morning.