Run Plan -- updated 11 May 2002. {Nominal start date - 5/22/02} I. Without the beam package: - establish operating point for chambers [2 days - day 2] measure efficiency for 120 MeV/c pions - Study beam **need plan here** [3 days - day 5] use straight through high momentum pions? other beams such as positrons? find focus (same as above, but not a dispersed beam) how much control do we have over the focus position, and beam size at TWIST entrance? - install trigger scintillator package [1 day - day 6] - set scintillator voltage and thresholds [1 day - day 7] - establish trigger in t_0 scintillators - obtain alignment and t_0 data [2 days - day 9] straight through particles at 120 MeV/c; running at 120 MeV/c, dispersed beam, multiple B2 settings (2000 Hz X 3600 X 20) events/day II. With full beam package - install rest of beam package (few hours) - commission PACT for use with scintillator - commission PACT for WC's establish DAQ and pedestal suppression [2 days - day 11] study gate and timing [1 day - day 12] study pulse height vs. operating volts [1 day - day 13] - study and calibrate the energy cuts in target PC's - stopping distribution [5 days - day 18] III. Take further alignment data for comparison after the run - 120 MeV/c pions [< 1 day - day 19] - Stop muons in spectrometer to spray the chambers with decay positrons [2 days - day 21] can use cloud muons, stop both upstream and downstream 200 Hz * 3600 * 20 => 10^7 per day {Valpo asked to come up with plan here} IV. Ready for field on - ramp to 2T in one day; take 30 minutes of pion data at 0.5, 1.0, 1.5 T? [1 day - day 22] V. Optimize beam - 30 MeV/c positrons, minimize beam p_perp as tracked through TWIST [4 days - day 26] (external downstream trigger only if needed) VI. Initial physics data - Study systematics of the stopping distribution get data with the target centroid shifted "slightly" upstream, centered, and "slightly" downstream; can we calibrate out the asymmetry in the energy calibration? We need roughly 24 hours of data @ 2KHz per position; stopping peak near edge of target may require more time; assume 5 X 24 hours of data, plus five days to play with the gas degrader, plus a fudget factor for settings with lower rates [14 days - day 40] - beta source alignment data; during a maintenance day [no time charge] - take data as a function of B field, look for change in the end point; one day at 2KHz => 22 hours X 3600 X 2000 = 1.6 X 10^8 triggers; assume a reduction factor of six => data set of 2.5X10^7; 1.98, 1.99, 2.01, 2.02T [4 days - day 44] - study effect of degrader material in the downstream end of the detector [4 days - day 48] - obtain cloud muon beam, stopped in the target [4 days - day 52] check that an RF cut can be used to get a beam which is roughly unpolarized. What is the upstream/downstream asymmetry? to obtain a comparable data set with a mixed beam at 200 Hz (that is, 2.5*10^7 in the fiducial volume, 10% beam rate) [20 days - day 72] - short run with 120 MeV/c pions [a few hours] - try to stop pions in target [1 day - day 73] - try to tune negative muons into detector for 0 polarization [2 days - day 75] VII. Wrap up, field off data - take more alignment data; straight through particles at 120 MeV/c [1 day - day 76] - stopped muons to spray detector [2 days - day 78] -------------------------- Beam off, ~ 3 September 2002 Subsequent running in October/November 2002 may be dedicated to: - studies of beam properties - commissioning of the TEC -------------------------- Note: Every two weeks, we get roughly 12 days of running time (ideally) Therefore, 76 days on this schedule takes at least three months. If we start the beam-related run plan near 22 May, then the above program would last at least until about 22 August. Beam is available until 3 September. It seems to me that we need to be careful about how we add things to the plan, and that discipline will be required to complete the plan.